Mandatory BIM in Kazakhstan: which facilities and from what date

Order No. 114 of the Minister of Industry and Construction of Kazakhstan introduces the mandatory use of TIMSO (information modelling technology for construction facilities, the local regulatory term for BIM) in three stages: from 1 August 2026, from 1 January 2028 and from 1 January 2030. Check your facility and find out what to prepare for state expert review.

We reply within one working day. NDA signed before you share any drawings.

10-second check

Is BIM mandatory for your facility?

Select the facility type from the list in Order No. 114. We will show the date from which an information model becomes mandatory.

Select a facility type

The list was approved by Order No. 114 of the Minister of Industry and Construction of Kazakhstan dated 19 March 2026.

Discuss your project

Three stages

Who is affected and when

From 1 August 2026

Already in force

  • Schools, gymnasiums and lyceums for 600+ students
  • Airports and passenger terminals
  • Tunnels and metro systems
  • Bridges 100 m or longer
  • Unique facilities

From 1 January 2028

Next stage

  • Residential and mixed-use buildings of 6+ storeys
  • Public and administrative buildings of 3+ storeys
  • Healthcare facilities, kindergartens with 95+ places
  • Stations, sports and entertainment venues for 150+ people
  • Energy, oil and gas, trunk utility networks

From 1 January 2030

All other facilities

  • All types of construction facilities except those of the third level of responsibility

What to submit for expert review

According to guidance from RSE Gosexpertiza, for facilities subject to TIMSO the design documentation is submitted together with:

  • an electronic model of the construction facility in IFC format;
  • the client's information requirements (EIR, known locally as ITZ).

The requirement covers both new construction and changes to existing facilities. Whether it applies is determined by the facility type and the date of the design contract. When submitting through the epsd.kz portal, the use of TIMSO is indicated in the project questionnaire.

Source: publication by RSE Gosexpertiza dated 20 August 2026 (in Russian).

What to check before submission

  • The IFC file opens and displays without errors
  • The model meets the client's requirements for the scope and content of the disciplines
  • The design solutions in the model match the documentation
  • The model is free of clashes: the check is run before submission

How to prepare the model

Full list

The 27 facility types in Order No. 114

№Facility typeMandatory from
From 1 August 2026
1General education school buildings (gymnasiums, lyceums) with a capacity of 600 students or more1 August 2026
2Airports, airport passenger terminals and other aviation infrastructure facilities1 August 2026
3Railway and road tunnels, metro systems1 August 2026
4Bridge structures 100 m or longer on roads of all categories1 August 2026
5Unique construction facilities1 August 2026
From 1 January 2028
6Preschool education facilities with 95 or more places1 January 2028
7Dormitory buildings of boarding schools and children's holiday camps with a capacity of more than 100 children1 January 2028
8Complexes of higher and secondary specialised education institutions (campuses, except stand-alone sports complexes, catering blocks, residential compounds and dormitory buildings)1 January 2028
9Residential and mixed-use buildings of 6 storeys or more (excluding the top technical floor)1 January 2028
10Administrative, amenity and public buildings and structures of 3 storeys or more (excluding the top technical floor)1 January 2028
11Gas distribution system facilities for residential and civil use with a pressure above 0.3 MPa1 January 2028
12Trunk oil pipelines and oil product pipelines of classes I, II, III and IV1 January 2028
13Trunk water supply and sewerage networks and their structures, water and wastewater treatment plants, pumping stations and water intakes with a capacity of 1,000 m³ per day or more1 January 2028
14Trunk and distribution (intra-block) heat supply networks with a nominal (internal) diameter of 320 mm or more and their structures1 January 2028
15Buildings of museums of national significance, state archives and repositories of national and cultural treasures that require special artificial climate systems and security measures1 January 2028
16Railway stations, bus terminals (bus stations), sea and river terminals1 January 2028
17Sports and entertainment venues and religious buildings, indoor or open-air, with a simultaneous occupancy (capacity) of 150 people or more1 January 2028
18Healthcare facilities, medical and preventive care institutions1 January 2028
19Power supply facilities, including substations, switchgear, overhead and cable power lines, and power supply centres1 January 2028
20Power plants of all types, including thermal, hydroelectric, solar, wind and other power generation facilities1 January 2028
21Oil and gas facilities, including production, field gathering, treatment, transportation, processing and storage of oil and gas, as well as liquefied natural gas facilities1 January 2028
22Category I and II motor roads and their structures1 January 2028
23Class I and II hydraulic structures1 January 2028
24Trunk railways1 January 2028
25Thermal power buildings and structures with a capacity of 150 MW or more1 January 2028
26Power transmission lines and other grid facilities with a voltage of 110 kV or more1 January 2028
From 1 January 2030
27All types of construction facilities, except facilities of the third level of responsibility1 January 2030

Source: Order No. 114 of the Minister of Industry and Construction of the Republic of Kazakhstan dated 19 March 2026, official text on adilet.zan.kz (in Russian). This is our unofficial translation: the official Kazakh and Russian texts prevail.

Legal basis

Where the requirement comes from

Construction Code
Code of the Republic of Kazakhstan No. 253-VIII of 9 January 2026, in force since 1 July 2026. Article 62(1) provides for a list of facilities for which TIMSO is mandatory.
Order No. 114
Order No. 114 of the Minister of Industry and Construction of the Republic of Kazakhstan dated 19 March 2026, in force since 1 July 2026. Official text (in Russian).
TIMSO
Information modelling technology for construction facilities. This is what Kazakhstan's regulations call the approach known worldwide as BIM. More about the term.
Standards for the model
SP RK 1.02-111-2017 “Application of information modelling in a design organisation” and RDS RK 1.02-04-2018 “Information modelling in construction. Basic provisions”.

Your facility is on the list but there is no model?

Send us the drawings. Within one working day we will tell you how long a model for expert review takes and what it costs.

Frequently asked questions

What is TIMSO?

Information modelling technology for construction facilities (the Russian abbreviation is ТИМСО). It is the name for BIM adopted in Kazakhstan's regulations: a facility is designed, built and operated on the basis of a single information model. We explain the term in our article.

From what date is BIM mandatory for schools?

For buildings of general education schools, gymnasiums and lyceums with a capacity of 600 or more students: from 1 August 2026. This is stage one and it is already in force. More on schools and kindergartens.

And for residential buildings?

For residential and mixed-use buildings of 6 or more storeys, excluding the top technical floor: from 1 January 2028. More on residential and public buildings.

Does the requirement apply to refurbishment?

Yes. According to guidance from RSE Gosexpertiza, the requirements apply both to new construction and to changes to existing facilities.

How do I know whether my project is covered?

Two things are considered: the facility type on the list, and the date of the design contract relative to the date set in the Order for that facility type. In borderline cases it is worth confirming the position with the local branch of the review body before submission.

What if we have no BIM team and the facility is already on the list?

The fastest route is to hand the modelling to a contractor while your team produces the documentation. We build models from drawings and prepare the EIR and the IFC package. In parallel you can start BIM implementation in-house.

Get a price and timeline

Describe the task or share a link to your drawings. Within one working day we will clarify the details and give you a price and a timeline. The initial assessment is free.

Offices
Almaty and London
Response
Within one working day

Your messenger will open with the request text ready. All you need to do is press Send.

WhatsAppGet a quote
Message us on WhatsApp